Energizing the 220kV Bao Lam substation and connected transmission line

Thứ ba, 27/12/2016 | 16:25 GMT+7
​​At 17h14 on November 29th 2016, the Central Power Projects Management Board (CPMB) combined with relevant units to organize energizing and putting into operation of 220kV Bao Lam substation and connected transmission line, completed project 1 month before assigned schedules.

220BaoLam_291116.JPG
The 220 kV Bao Lam substation

​The energized “220kV Bao Lam substation and connected transmission line” project will ensure the capacity transmission of hydropower plants in Bao Lam, Bao Lac districts of Cao Bang province and surrounding areas to the national power system. This brings in an income for the socio-economic and national defense development in Cao Bang mountainous province; ensuring power energy for a sustainable development of Cao Bang province and Northern mountainous provinces; increase power quality in the area and brings into full play the transmission capacity of existing transmission grid. The project is also to responds to the Customer Gratitude month – December 2016 of Vietnam Electricity (EVN).

The project has a total cost of VND 323.66 billion mobilized from commercial banks and EVNNPT’s equity, invested by National Power Transmission Corporation (EVNNPT); CPMB is on behalf of EVNNPT to manage the project; Power Engineering Consultation Company No. 1 (PECC1) is responsible for design; Power Construction Company No. 1 is responsible for project implementation, Northern Testing One-Member Limited Liability Company is responsible for testing; Power Transmission Company No. 1 (PTC1) will take over the management and operation of project.

Scope of project: (i) New construction of 220 kV substation of capacity 2x125 MVA, with installing a 125 MVA transformer at this stage; (ii) Construction of double circuit 220kV transmission line, of a 14.2km length from 220 kV Bao Lam substation connected in a circuit of of 220 kV Nho Que - Cao Bang transmission line; (iii) Construction of 1 circuit 35kV transmission line of a 1,095 m length to serve the auxiliary power in the substation.

The project started on December 15th 2015 and constructed in Na Mat village, Ly Bon commune, Bao Lam district of Cao Bang province./.​