Completing project “Overhaul of 500kV reactor at 500kV Nho Quan substation”

Thứ ba, 29/11/2016 | 09:45 GMT+7
​​At 14h40, on October 28th 2016, Ninh Binh Power Transmission (under Power Transmission Company No. 1 – PTC1) and relevant units organized commissioning, energizing and putting into operation the KH504 shunt reactor, completing project on overhauling 500kV, KH501, KH504 shunt reactors at 500kV Nho Quan substation.

KhangKH504_011116_1.JPG
The overhauled KH504 shunt reactor energized

This is an overhaul project in 2016 which is selected bu PTC1 as one of focal tasks in 2016. Before that, on September 9th 2016, Ninh Binh Power Transmission under PTC1 energized and put into operation the KH501 shunt reactor.

The energizing of overhauled KH501, KH 504 shunt reactors contributes to increasing flexibility in voltage allcation in power system, in general and 500kV power grid in particular, reducing power loss in transmission grid, increasing transmission capacity in the 500kV North-South transmission line sections. This is a premise for PTC1 to settle the similar shortcomings for the existing 500kV shunt reactors in transmission grid.

The project is implemented by Anh Duong – Sai Gon limited Liability Company, the supervising, testing, commissioning units include: Testing Division, Power Equipment Repair Division, Ninh Binh Power Transmission under PTC1.

KhangKH504_011116_2.JPG
Operation done before energizing

To push up the implementation process for an early energizing, PTC1 leaders guided functional Divisions and units to cooperate with National Load Dispatch Centre (A0) to develop an optimal power-cut schedules as well as guided the implementing units to organize a detail implementing plan at site so that the project is implemented as scheduled.

The project implementation is done in the complicated weather conditions: long duration of hottest weather (for KH501 shunt reactor) and long duration of rain (for KH504 shunt reactor), severely affected by storm No. 6 and 7, but work load is huge and complicated, which require a strict technical procedures.

However, with the high determination and guidance by PTC1 leaders of PTC1, Ninh Binh Power Transmission and workers of implementing units have completed the project successfully./.​