Energizing project “Hanging 2nd circuit of 220kV Hoa Khanh – Hue transmission line”

Thứ ba, 8/11/2016 | 16:35 GMT+7
​At 14h00 on September 16th 2016, at 220kV Hoa Khanh substation of Da Nang city, Power Transmission Company No. 2 (PTC2) organized commissioning, energizing and putting into operation of project “hanging 2nd circuit of 220kV Hoa Khanh – Hue transmission line”.

220HKH_160916_2.jpg
Implementing project “hanging 2nd circuit of the 220kV Hoa Khanh – Hue transmission line


In order to ensure power supply to Thua Thien Hue and Quang Tri provinces from 500kV Da Nang substation and evacuate capacity of hydropower plants in Western Quang Nam province through the 220kV Hoa Khanh – Hue transmission line, the National Power Transmission Corporation (EVNNPT) invested over VND 106 billion and assigned Power Transmission Company No. 2 (PTC2) to be on behalf of EVNNPT to carry out project “hanging 2nd circuit of the 220kV Hoa Khanh – Hue transmission line”.


This is the level 1 energy project. The transmission line includes 2 circuits of 82km length (circuit was energized on July 15th 2002) running through Lien Chieu ward, Hoa Vang district, Da Nang city and Phu Loc district, Huogn Thuy, Hue city of Thua Thien Hue province.


Mr. Nguyen Tien Dung – Vice Director of PTC2 revealed that during the project implementation, investor and contractor – Vietnam Power Construction Corporation have faced many difficulties. Almost half of transmission line runs over 4 passes of Hai Van, Phu Gia, Phuoc Tuong, Mui Ne, terrain conditions for project implementation are comlicated; Besides, compensation and site clearance were difficult, involving over 340 households who are mainly in Hoa Vang district, Lien Chieu district of Da Nang city. However, with the support by local authorities, PTC2 and implementing unit together with local compensation councils organized propaganda and mobilized people to accept the site clearance for project implementation.


Apart from hanging 82km of 2nd circuit 220kV transmission line, PTC2 has installed 30 surge arrestors in the 2nd circuit; constructed a new 220kV outdoor feeder at 220kV Hoa Khanh substation and 220 kV Hue substations, including construction and installation of 220kV circuit breakers , 220kV disconnectors, 220kV current transformer, 220kV voltage transformer, protection control and measurement systems…


The completion of project will strengthen 220kV power grid connection in Central coastal areas, increase the connection in 220kV side of 500kV Da Nang substation and 500kV Phong Dien substation (Thua Thien Hue province), as well as strengthen the evacuation of capacity from 500kV Da Nang substation to 220kV Hue, Dong Ha substations, meeting n-1 requirement, minimizing power transmission loss and ensuring a power supply for socio-economic development of the provinces in coming years./.

Operations

Operations

Investment

Investment

International relations

International relations

Event Calendar

Event Calendar