Completing project “Installing 220kV transformer at 500kV Thuong Tin substation"

Thứ hai, 26/9/2016 | 17:15 GMT+7
​At 11h30, on August 16th 2016, Hanoi Power Transmission (under Power Transmission Company No. 1) combined with relevant units organized commissioning and energizing remaining 5 110kV feeders of Phase 2, completing project “Installing 220kV transformer at 500kV Thuong Tin substation", which is to supply power to the 110kV transmission lines of EVNHANOI. This is one of the important premises to ensure the project’s general progress, meeting the load development as regulated in National Power Development Plan No. 7.
DD220-500TT_200816_1.jpg
The 110 kV equipment system at 500 kV Thuong Tin substation 

The project energized will be to exploit capacity of the North Eastern thermal power plants, supply power to the Southern loads of Hanoi city and surrounding areas; meeting the rapid and continuous growing loads of Hanoi city last time, contributing to increasing the stability and secure, reliable operation of Norther power transmission grid.

This is the energy project of level 1, group B, with total cost of over VND 254 billion invested by National Power Transmission Corporation (EVNNPT), PTC1 is on behalf of EVNNPT to manage the project, Power Engineering Consultation Company No. 4 (PECC4) is responsible for project design, Power Construction Company No. 4 (PCC4) is responsible for project construction. Participating in the construction includes PTC1’s subsidiaries such as Power Testing Division, Power Equipment Maintenance and Repair Division, Hanoi Power Transmission, 500kV Thuong Tin substation.

The project scope is to install a 220kV-250MVA transformer; toward 220kV: 1 transformer bay, 1 transformer feeder, 1 liaise feeder, 6 out-going bays, 3 spare feeders, the expanded construction area is 16,594 m2.

DD220-500TT_200816_2.jpg
Mr. Nguyen Huu Long – PTC1 Vice Director, Chairman of Project Commissioning Council chaired the meeting

The project is divided into 2 phases:

- Phase 1: Completed and energized in May 2013, with a scope of installing one 220/110/22kV-250MVA transformer (AT3); installing one 110kV general feeder and two 110kV out-going feeders lead to 110kV Thuong Tin substation.

- Phase 2: To expand substation area of over 16,594,000 m2 for 110 kV switch yard; install 8 110kV feeders, 5 of which will use new primary and secondary equipment, remaining 3 feeders removed primary equipment installed in phase 1 to the new location. PTC1 has removed 3 feeders and energized on December 12th 2015; 05 remaining feeders were energized on August 16th 2016.

DD220-500TT_200816_3.JPG
Operation before energizing

The in-time completion of project was gained thanks to efforts, devotion, responsibility by various units such as PTC1, 500kV Thuong Tin substation, Hanoi Power Transmission, Equipment Maintenance and Repair Division, Power Testing Division, Mechanical Transportation Division, etc… Besides, is was provided with support by local authorities, Thuong Tin People’s Committee and various Departments under Hanoi city, Hanoi People’s Committee, which have guided and combined in implementing the site clearance and compensation for project’s land acquisition. The project implementation was done in the most severe weather conditions, with safety ensured for people, equipment, in which Hanoi Power Transmission has implemented well the assigned tasks: tensioning over 20,000m secondary cable, installed the out-door and in-door cabinets, installed grounding system for protection control cabinets, connected secondary equipment for all protection control circuits, Scada optical cable system, completed connection of nearly 2,000m AAC-885 conductor, as well as participated in monitoring and combined with different units such as Testing Division, Equipment Maintenance and Repair Division, implemented project as required schedule and quality./.