Energizing and putting the AT2 220kV-250MVA transformer at 220kV Thanh Hoa substation into operation

Thứ sáu, 30/9/2016 | 15:20 GMT+7
​​At 23h05 on August 30th 2016, Power Transmission Company No. 1 combined with relevant units to organize energizing, commissioning and putting into operation the AT2 220kV-250MVA transformer at 220kV Thanh Hoa substation, completing project “Upgrade capacity of 220kV Thanh Hoa substation”.
NCS220ThanhHoa_050916_5.jpg
The meeting of Project Commissioning Council chaired by Mr. Nguyen Huu Long – Vice Director of PTC1, Chairman of Project Commissioning Council

The project completion is very important, contributing to strengthening the power supply, increasing the reliabilities of the system and meeting the socio-economic development demands of Thanh Hoa province; the project is to celebrate 71 anniversary of August Revolution and Independence Day –September 2nd of the Socialist Republic Vietnam. After project completed, the 220kV Thanh Hoa substation will be increased from (125+250)MVA to (2x250)MVA capacity.

This is the energy project of level 1, group C, with scope of replacing the existing AT2 220kV-125MVA transformer by the 220kV-250MVA one; adding, replacing, installing the relevant equipment to fit with the new transformer.

The project has a total cost of VND 68 billion invested by EVNNPT, SPMB is on behalf of EVNNPT to manage the project, Power Engineering Consultation Company No. 4 (PECC4) is responsible for project design; Song Da Construction ans Services company is responsible for project construction; Dong Anh Electrical Equipment Corporation (EEMC) provides transformers. Besides, participation in project construction also includes PTC1’s subsidiaries: Thanh Hoa Power Transmission, Power Testing Division, Power Equipment Maintenance and Repair Division.

With the strictly technical requirements for equipment, a big load of works together with substation management, short time power cut-off (3 days) for implementation, but with high determination, overcoming any difficulties, with sufficient equipment and tools, the project “Upgrade capacity of 220kV Thanh Hoa substation” has completed as scheduled, securely energized and operated, ensuring the quality requirements. 

NCS220ThanhHoa_050916_4.jpg
The AT2 220kV-250MVA transformer and all 220kV system energized and operated

During the project implementation, to ensure safety, [rpgress and quality of project, Board of Directors, Labour Union, functional Divisions of PTC1 and leaders of Thanh Hoa Power Transmission have spent many time at site, encourage and create favourable conditions for all staff and implementing units so that they can complete project well./.