Energize and put into operation AT2 500kV-900MVA transformer at 500kV Thuong Tin substation

Thứ ba, 27/12/2016 | 16:30 GMT+7
​At 1.20 PM on December 3, 2016, the Power Transmission Company 1 (PTC1) in collaboration with the relevant units has energized and put into operation  AT2 500kV-900MVA transformers at Thuong Tin 500kV substations and has completed phase 1 of the project "Upgrading the capacity of 500kV Thuong Tin substation" with the  construction time of one day premature schedule compares to the plan.

MBA500ThuongTin_051216.jpg 

The project "Upgrading the capacity of 500kV Thuong Tin substation" has a total investment cost of over 280 billion Vietnamese dong and the National Power Transmission Corporation (EVNNPT) is the investor; PTC1 is the one who operates and manages the project on behalf of EVNNPT; The project was designed by Power Electric Consultancy Company 4 (PECC4); monitor by Power Inspection Design Construction Company 4 (PIDC4); and Construct by Song Da Construction and services Joint Stock Company. Also, PTC1 also assigned to its units: Material Repair   Workshop, Testing Workshop, Mechanical Transport Team, Hanoi Power Transmission Branch assign dozens of engineers and workers regularly available at 500kVThuong Tin substation to continuously construct, supervise and commission works as soon as the contractor has completed to catch up the planned schedule.

The project has started on November 25, 2016  includes 2 stages: Stage 1: Replace the existing AT2 500kV-600MVA transformer by 500kV-900 MVA, supplement and replace suitable equipment to the new transformer; Stage 2 will be  implemented in 2017 and the second 220kV transformer will be installed as well as new 220kV, 110kV bays.

This is the project with huge amount of works while power cut time for construction is so limited and high technical requirement. There are dozens of engineers and workers from different contractors of different categories on a narrow construction site, all the contractors have calculate and coordinate very closely, even have divided into shifts to construct uninterruptedly almost 24/24 in order to ensure the project progress, quality as well as the safety. Thereby, after 09 days continuous construction, the Upgrading the capacity of 500kV Thuong Tin substation has successfully commissioned, energized  one day earlier than planned schedule.

The early energizing and commissioning of AT2 500kV-900MVA transformer at 500kV Thuong Tin substation will be timely solve the overload for the station, especially at the end of the year and the upcoming Lunar New Year; ensuring power supply safety and reliability for the load of Hanoi city and the surrounding areas; simultaneously increases stability, safe operation of the grid; reduces power losses of the grid, contributes to the improvement of business efficiency.

This is the achievement of employees of PTC1 in particular and EVNNPT in general to celebrate 62 years of Vietnam traditional power sector (21/12/1954 – 22/12/2016). It is also the practical activities in responding the month "Customers Gratitude" - 12/2016 of the Vietnam Electricity./.