Energizing and putting into operation the AT1 220kV-250MVA transformer at 220 kV Binh Long substation

Thứ sáu, 16/6/2017 | 16:35 GMT+7
​At 01h15, on 12th June 2017, at 220kV Binh Long substation (in Thanh Tuan village, Thanh Luong commune, Binh Long town, Binh Phuoc province, Power Transmission Company No. 4 (PTC4) and relevant units organized commissioning, energizing the AT1 220kV-250MVA transformer, increasing the substation’s capacity from (1x125 + 1x125) MVA to (1x125 + 1x250) MVA.

AT1_220BinhLong_120617.jpg
The AT1 220 kV - 250 M​VA transformer at 220 ​kV Binh Long substation

The energizing and putting into operation AT1 transformer will strengthen reliability and transmission capacity of 110kV transmission grid in Binh Phuoc province, which is in accordance with the provincial power development plan, meeting the growing load demands of Binh Long, Loc Ninh, Dong Phu and Dong Xoai towns, contributing to increasing production efficiency of EVNNPT.

Project “Upgrading capacity of 220kV Binh Long”, with total cost of VND 51 billion invested by EVNNPT. PTC4 is on behalf of EVNNPT to manage the project and manage the operation of project after its completion. Power Engineering Consultation Company No. 3 (PECC3) is responsible for project design. Song Lam Investment and Construction Joint Stock company is responsible for project implementation.

The scope of project: Replacing the existing AT1 220kV-125MVA transformer at 220 kV Binh Long substation by a 220kV-250MVA one; improvement of foundation, replacing and supplementing some equipment to make suitable to the new transformer./.​