Implementing five 220kV substation projects

Thứ ba, 21/2/2017 | 16:20 GMT+7
​On December 25th 2016, 5 220kV substation projects including Luu Xa, Nong Cong, Phong Dien, Phu My and Dak Nong were commenced by Central Power Projects Management Board (CPMB) together with implementing contractors, local authorities and relevant agencies.

The projects are invested by the National Power Transmission Corporations (EVNNPT), CPMB is on behalf of EVNNPT to manage the projects. The projects are expected to be completed from Quarter IV/2017 to Quarter II/2018. 

The 220kV Luu Xa substation put into operation will contribute to meeting the rapid load growth demands in Thai Nguyen province; increasing power quality, reliability and flexibility in operation and power supply of the regional power grid, reducing power loss in power grid, ensuring energy security for the socio-economic development in Thai Nguyen province.

CPMBKC5TBA_251216_1.jpg
Commencement of 220kV Luu Xa substation

The 220kV Nong Cong substation put into operation will contribute to strengthen meeting the load demands in Thanh Hoa province; supporting and reducing load for 220kV Nghi Son and Thanh Hoa substations; strengthening the regional power system connection, increasing security, reliability and stability in operation of National power system and limiting transmission loss, increasing business and production efficiency in EVNNPT.

CPMBKC5TBA_251216_2.jpg
Commencement of 220kV Nong Cong substation

The 220kV Phong Dien substation put into operation will ensure meeting the rapid load growth demands in Thua Thien Hue province in general, in the provincial North in particular, with many critical large-scale industrial zones; increasing power quality, reliability – flexibility in operation and power supply of regional power grid; reducing power loss in power network; ensuring energy security for the socio-economic development demands in Thua Thien Hue province.

CPMBKC5TBA_251216_3.jpg
Commencement of 220kV Phong Dien substation

The 220kV Phu My substation is constructed in synchronization with the 220kV Quang Ngai – Quy Nhon transmission line project. Its completion will meet a reliable, stable and permanent power supply for Binh Dinh load demands when the system is in normal operation and even when it fails; reducing power loss in regional power system.

CPMBKC5TBA_251216_4.jpg
Commencement of 220kV Phu My substation

The 220kV Dak Nong substation put into operation will strengthen power supply, meeting the growing load demands in Dak Nong province, when Nhan Co bauxite and aluminum power plant started, contributing to increase the reliability, security, stability in operation, power quality for the regional power system and limit power transmission loss, increase production and business efficiency in power sector.

CPMBKC5TBA_251216_5.JPG
Commencement of 220kV Dak Nong substation

Up to now, CPMB started 10 projects, which indicates the high efforts by CPMB staff in particular and EVNNPT in general in order to welcome the power sector traditional day 21st December and response to “customer gratitude” month – December 2016 by Vietnam Electricity (EVN) and EVNNPT.

Some basic information:

1. 220kV Luu Xa substation

- Comtractor: Song Da Installation and Services Joint Stock Company .

- Total investment cost: VND 269.699 billion.

- Scope of works: (i) New construction of a 220kV substation, of two 220kV-250MVA transformers, with 1 transformer installed in this period; (ii) Construction of 220kV transmission line section, of a 0.94km length connecting from 220kV Luu Xa substation to 220kV Thai Nguyen – Phu Binh transmission line; (iii) Construction of a 220kV transmission line of 727.8m length for auxiliary power use purpose.

- Location: Duc Thinh commune, Thai Nguyen city, Thai Nguyen province.

2. The 220kV Nong Cong substation

- Contractor: Vietnam Installation Joint Stock Corporation .

- Total investment cost: VND 434.694 billion

- Scope of works: (i) New construction of 220kV substation, of 02 220kV-250MVA transformers, with 1 AT2 transformer installed in this phase, 1 AT1 transformer to be installed in phase 2; (ii) Construction of 2 double circuit 220kV transmission line sections to connect from 220kV Nghi Son – Thanh Hoa transmission line (circuit 2) to substation in this phase, with a length of 1,353 m and 1,398 m.

- Location: Huu Can village, Te Loi commune, Nong Cong district, Thanh Hoa province.

3. The 220kV Phong Dien substation

- Contractor: Song Da Installation and Services Joint Stock Company .

- Total investment cost: VND 205.140 billion.

- Scope of works: (i) New construction of 220kV substation, semi-outdoor, semi-indoor, of 2 220kV-125MVA transformers, with 1 transformer installed in this phase; (ii) Construction of a double circuit 220kV transmission line section of a 1,346 m length connecting from 220kV Phong Dien substation to 220kV Dong Ha – Hue transmission line; (iii) Construction of one circuit 22kV transmission line of a 936 m length for auxiliary power use purpose.

- Location: Phong Thu commune, Phong Dien district, Thua Thien-Hue province.

4. Trạm biến áp 220kV Phù Mỹ

- Contractor: Vietnam Power Installation Joint Stock Corporation

- Total investment cost: VND 241.311 billion.

- Scope of works: (i) New construction of 220kV substation, of two 220kV-125MVA transformers, with 1 transformer installed in this phase; (ii) Construction of 220kV distribution system including 8 feeders and 110kV distribution system including 15 feeders; (iii) Construction of double circuit 220kV transmission line, with total length of about 1.712 km connecting to the 220kV Quang Ngai – Quy Nhon transmission line which is under construction; (iv) Construction of a circuit 22kV transmission line of about 668m length for auxiliary power use purposes.

- Location: Trung Hoi village, My Trinh commune, Phu My district, Binh Dinh province.

5. The 220kV Dak Nong substation

- Contractor: Power Installation One-Member Limited Liability Company 2.

- Total investment cost: VND 364.085 billion.

- Scope of works: (i) New construction of 220kV substation, of 02 220kV-125MVA transformers; (ii) Construction of a double circuit 220kV transmission line, of a 1.19 km length, separating 1 circuit from 220kV double circuit transmission line at 500kV Dak Nong substation to 220kV substation at Aluminum power plant; (iii) Construction of 220kV transmission line of a 0.45 km length for auxiliary power use purpose.

- Location: Village 12, Nhan Co commune, Dak R’lấp district, Dak Nong province.​​