Successfully energizing K504 circuit breaker at 500 kV Vung Ang substation

Thứ sáu, 23/9/2016 | 07:55 GMT+7
​​At 22h50, on July 31st 2016, a project commissioning council of National Power Transmission Corporation (EVNNPT) organized commissioning and energizing the K504 circuit breaker at 500 kV Vung Ang substation.
KhangVungAng_020816_2.JPG
Successfully energizing the K504 circuit breaker at 500 kV Vung Ang substation

The energizing K504 circuit breaker at 500 kV Vung Ang substation contributed to increase of flexibility in voltage adjustment in the power system in general and 500kV power grid in particular, reduce power transmission loss, increase power transmission capacity in the 500kV transmission line routes.

It is one of eleven 500kV circuit breakers of project “Equiping circuit breakers for shunt reactors in 500kV power grid” which is allocated by EVNNPT to Power Transmission Company No. 3 (PTC3). Accordingly, from July 24th 2016 to August 1st 2016, PTC3 carried out installation of one 500kV circuit breaker and adjustment of protection control system, computerized control system, SCADA for the KH504 reactor of the 500kV Vung Ang – Da Nang transmission line.

KhangVungAng_020816_1.jpg
Installation of K504 circuit breaker

3 days before power cut-off for project installation, over 30 staff together with mechanical tools, equipment of Mechanical Power Factory, Power Testing Division, Transportation Vehicle Division under PTC3 have been moved a distance of over 950km from Nha Trang city to the 500 kV Vung Ang in Ky Anh, South of Ha Tinh province to be ready for the installation of reactor circuit breaker.

Despite of difficult weather conditions of hottest time in North Central area, but with high efforts and responsibilities by implementing uits, together with support by National Load Dispatch Centre (NLDC), Power Transmission Company No. 1 (PTC1), Ha Tinh Power Transmission, 500kV Vung Ang substation and the equipment supply contractors, the implementing units has completed the project as scheduled./.

Project scope:

“Equiping circuit breaker for shunt reactor in 500kV power grid” project includes of 2 phases:

- Phase 1: Install 12 circuit breakers (CB) for shunt reactor at the 500 kV substations (in which 11 circuit breakers installed by PTC3). At present, PTC3 has completed installation of 10 circuit breakers at the 500 kV substations: Nho Quan (02), Dak Nong (01), Di Linh (01), Pleiku (03), Thanh My (01), Ha Tinh (01), Vung Ang (01).

- Phase 2: Install 10 CB for shunt reactor at the 500 kV substations, in which 9 CB to be installed by PTC3 at 500kV substations: Hoa Binh (01), Son La (04), Quang Ninh (02), Vinh Tan (02).