Energizing the 2nd 220kV transformer at 220kV Bao Thang substation
08:25 | 29/07/2018
At 20h45 on July 26th 2018, at
Phu Nhuan commune, Bao Thang district, Lao Cai province, the Northern Power
Projects Management Board (NPMB) combined with relevant units have energized
the 220/110/22kV-250MVA transformer, completing project “Installing the 2nd 220
kV transformer at 220kV Bao Thang...