AT2 220kV-250MVA transformer at 220kV Nam Dinh
substation
The energization and putting into
operation of AT2 220kV-250MVA transformer MBA at 220kV Nam Dinh substation not
only provides electricity directly to Nam Dinh, Thai Binh and Ha Nam provinces
but also plays an important role in ensuring the national power transmission
network safe, stable, contributing to the social-economic development, security
and defense of the Southern Red River delta.
The project "Increasing the
capacity of 220kV Nam Dinh substation from (125 + 250) MVA up to 2x250MVA"
has the total investment of over 84 billion with the National Power
Transmission (EVNNPT) as the investor; Power Engineering Consulting joint stock
company 3 (EVNPECC3) as designing consultant, units of Power Transmission company
1 (PTC1); Equipment repair workshop, Ninh Binh power transmission company, Experiment
workshop responsible for the implementation.
The project has a total construction
and investment: replacing the existing 220kV- 125MVA transformer with a
220kV-250MVA transformer; replacing and installing additional equipment to suit
the new transformer.
The construction was started on
29/05/2015 inside Nam Dinh 220kV substation and located in My Phuc commune, My
Loc district, Nam Dinh province./.