The delegates attended in Ceremony on summarizing emulation for the 220kV Dak Nong – Phuoc Long – Binh Long T/L and launching a joint emulation movement for the 500kV Pleiku- My Phuoc – Cau Bong T/L
Participation in the event includes Mr. Dang Ngoc Tung – Member of Central Party, Chairman of Vietnam General Confederation of Labour (VGCL); Mr. Duong Quang Thanh – Vice President of Vietnam Electricity (EVN); Mr. Khuat Quang Mau – Vice Chairman of EVN’s Labour Union; Mr. Dang Phan Tuong – Chairman of EVNNPT’s Management Board; Mr. Nguyen Manh Hung – EVNNPT’s President and CEO; leaders of PTC3, PTC4; leaders of Central Power Projects Management Board (CPMB), Southern Power Projects Management Board (SPMB), contractors, power construction companies as well as the authorities of localities where the T/L run through.
The 500kV Pleiku- My Phuoc – Cau Bong T/L project is investmented by EVNNPT. The project management is under CPMB. This is a critical project, aiming at supplying power to the increasing load demands in the South for 2014 – 2015 period; creating a premise for importing power from Laos to Vietnam and interconnection of power grid of 3 countries of Vietnam – Laos – cambodia in period after 2015. The project strengthens connection of the 500kV transmission grid, contributing to ensuring a safe and economic operation of power system when the high-level energy exchange is required among the regions in whole country. The project run through 5 provinces of Gia Lai, Dak Lak, Dak Nong, Binh Phuoc, Binh Duong and Ho Chi Minh city, with a length of 437.514 km, a total investment of over VND 9,288 billion.
__12.JPG)
Mr. Dang Ngoc Tung – Member of Central Party, Chairman of Vietnam General Confederation of Labour (VGCL) granted certificate of merit to collective, individuals who gained excellent achievements in movement.
On this occation, EVNNPT also summarized a joint emulation for the 220kV Dak Nong – Phuoc Long – Binh Long T/L. This is a critical project, meeting the urgent demand on transfering power from hydropower plants in Western Highlands into the national power system; strengthening the sufficient power supply to the South in coming years and ensuring the stable operation of power system. Especially, the project aims to set up a connection of 220kV transmission grid between Western Highlands and the South from now to after 2020.
The project is under investment by EVNNPT, under management by CPMB on behalf of EVNNPT. It has a total investment of VND 1,389.66 billion, its construction was commenced in September 2011.
Being implemented in the context of many difficulties, both in finance and compensation and site clearance, the investor and implementing units of the 220kV Dak Nong – Phuoc Long – Binh Long have made high efforts during the project implementation. Apart from the close direction by the Government, the involvement by the local authorities of provinces where the T/L run through, the join emulation movement at site has a high importance in creating an impulse to push up the project “to be completed” as scheduled.
Concretely, in July 20th 2012, EVNNPT and EVN’s Labour Union organized a ceremony on launching a joint emulation movement at site. The movement has created an impetus for the project progress, creating an impulse for implementing units to concentrate resources and equipment, handle all the difficulties o push up the project progress.
At the time of launching the emulation movement (July 20th 2012), the project has completed only 85% of foundation, with constraints found in many locations because of the compensation and site clearance, uninspected right-of-way, undelivered and unerected towers. After 5 month construction, despite the large amount of work has not been done, thanks to the emulation movement at site by implementing units, the project has been completed as scheduled CPMB organized well propaganda before and after the emulation movement launch, organized public meetings to promulgate the policies, purposes and benefits of project, which help them in achieving a large agrement among people. Most of people in the area have a clear understanding and support the project, facilitate to push up the project progress.
The 220kV Dak Nong – PHuoc Long – Binh Long completed as scheduled, which brings in many valuable experiences. Those are the lessons on direction, management, compensation and site clearance, effective coordination of all units participating in project, the high concentration of forces to “sprint” in the significant periods of project.
The success of this project contrinutes to creating a driving force of the big transmission projects such as the 500kV Pleiku- My Phuoc – Cau Bong to be implemented in favourable conditions.
Some photos taken at the ceremony:
_8.JPG)
Mr. Dang Ngoc Tung – Member of Central Party, Chairman of Vietnam General Confederation of Labour (VGCL) made a speech at the ceremony
__7.JPG)
Mr. Duong Quang Thanh – EVN’s Vice President made a speech at the ceremony
_11.JPG)
EVNNPT carried out the emulation movement for the 500kV Pleiku - My Phuoc - Cau Bong