EVNNPT’s President and CEO Nguyen Manh Hung checked the implementation of the 500kV Pleiku- My Phuoc – Cau Bong in the first days of lunar new year 2014

Thứ sáu, 7/3/2014 | 00:00 GMT+7
​From 10th  - 11th February 2014, Mr. Nguyen Manh Hung – President and CEO of National Power Transmission Corporation (EVNNPT) had a site visit to the  500kV Pleiku – My Phuoc – Cau Bong transmission line.

​Participation in the mission were representatives of EVNNPT’s functional Departments of Construction Management, Administration, leader of Central Power Projects Management Board (CPMB) and its representatives of Divisions of Technical,  Compensation, Planning and General Administration.
After checking the project implementation, Mr. Nguyen Manh Hung highly appreciated the efforts by contractors who have gathered its human resources and equipment for the project implementation during Giap Ngo 2014 Tet holidays and after Tet; He also required the contractors to mobilize more human resources and equipment to carry out the simultaneous implementation in right of way; Besides, he required CPMB to better bring into play experiences and achievement gained in project execution, actively and effectively cooperate with relevant units, Power Transmission Company No. 3, 4 to arrange sufficient human resources to monitor the implementation by contractor, push up the check and take over, with the aim that the check and take over will be completed after conductor tension finished. This is to ensure that the project will be energized in April 2014 to meet requirements on power supply to Ho Chi Minh city, in particular and the South, in general, in 2014 dry season.
On behalf of the mission, President and CEO Nguyen Manh Hung gave warm regards and gifts to encourage workers, monitor engineers who spent lot of time at site.
Also in the mission, Mr. Nguyen Manh Hung met and thanked the support provided to EVNNPT by leaders of People’s Committees of Cu Chi district, Ho Chi Minh city, of Ben Cat district, Binh Duong province. Besides, he recognized CPMB’s participation in compensation, site clearance over the last time and asked localities for providing EVNNPT with further support so that compensation and site clearance will be completed, ground will be transferred to the contractor for implementation.
 
Some photos during the mission:
  bai dich ngay tet (11).jpg
Mr. Nguyen Manh Hung – EVNNPT’s President and CEO visited the implementing unit – Power Construction
JSC No. 2 is implementing a feeder in the 500kV Cau Bong substation
  bai dich ngay tet (12).jpg
Mr. Nguyen Manh Hung – EVNNPT’s President and CEO visited the monitoring consulting unit – Power Transmission
JSC No. 4 is monitoring the implementation of feeder in the 500kV Cau Bong substation
bai dich ngay tet (13).jpg
Workers of Power Construction JSC. No. 2 were happy when receiving gift by
Mr. Nguyen Manh Hung – EVNNPT’s President and CEO
  bai dich ngay tet (14).jpg
 Mr. Nguyen Manh Hung – EVNNPT’s President and CEO visited implementing
unit – Power Construction JSC No. 1 is carrying out the conductor tension
bai dich ngay tet (15).jpg
Worker of Power Construction JSC. No. 1 is carrying out conductor tension
 bai dich ngay tet (16).jpg
Conductor with sag has been tensed
 