The AT2 220kV-125MVA transformer
The energization of AT2 transformer
will reduce load for the existing AT1 220/110/22kV transformer at 220 kV Yen Bai
substation; contributing to evacuating capacity of small- and medium-scale
hydropower plants in Yen Bai, Lao Cai, Lai Chau provinces and surrounding
provinces to the national power system; increasing the reliabilities,
flexibility in operation and management, reducing power loss in transmission
grid of NorthWestern area; meeting the socio-economic development demand in Yen
Bai province and surrounding areas.
The project is invested by National
Power Transmission Corporation (EVNNPT).
NPMB is on behalf of EVNNPT to manage
the project; Institute of Energy is responsible for project design; AlphaNam
E&C Joint Stock Company is responsible for project implementation; Vietnam Energy
Trade and Technical Joint Stock Company is in charge of project testing, Power
Transmission Company No. 1 is responsible for project monitoring and taking
over the project management and operation after completion.
This is the energy project of grade
1, Group C. It has a scope of: installing a 3 phase AT2 220/110/22kV
transformer of 125 MVA capacity; installing equipment of feeders at 220kV,
110kV, 22kV of AT2 transformer; supplementing protection control and
measurement system; supplementing SCADA data to AT2 transformer and switching
equipment.
The
project is implemented in the 220 kV Yen Bai substation, at Tan Thinh commune,
Yen Bai city, Yen Bai province./.