The projects are invested by the National Power
Transmission Corporations (EVNNPT), CPMB is on behalf of EVNNPT to manage
the projects. The projects are expected to be completed from Quarter IV/2017 to
Quarter II/2018.
The 220kV Luu Xa substation put into operation
will contribute to meeting the rapid load growth demands in Thai Nguyen
province; increasing power quality, reliability and flexibility in operation
and power supply of the regional power grid, reducing power loss in power grid,
ensuring energy security for the socio-economic development in Thai Nguyen
province.

Commencement
of 220kV Luu Xa substation
The 220kV Nong Cong substation put into
operation will contribute to strengthen meeting the load demands in Thanh Hoa
province; supporting and reducing load for 220kV Nghi Son and Thanh Hoa
substations; strengthening the regional power system connection, increasing
security, reliability and stability in operation of National power system and
limiting transmission loss, increasing business and production efficiency in EVNNPT.

Commencement
of 220kV Nong Cong substation
The 220kV Phong Dien substation put into
operation will ensure meeting the rapid load growth demands in Thua Thien Hue
province in general, in the provincial North in particular, with many critical
large-scale industrial zones; increasing power quality, reliability – flexibility
in operation and power supply of regional power grid; reducing power loss in
power network; ensuring energy security for the socio-economic development
demands in Thua Thien Hue province.

Commencement
of 220kV Phong Dien substation
The 220kV Phu My substation is constructed in
synchronization with the 220kV Quang Ngai – Quy Nhon transmission line project.
Its completion will meet a reliable, stable and permanent power supply for Binh
Dinh load demands when the system is in normal operation and even when it fails;
reducing power loss in regional power system.

Commencement
of 220kV Phu My substation
The 220kV Dak Nong substation put into
operation will strengthen power supply, meeting the growing load demands in Dak
Nong province, when Nhan Co bauxite and aluminum power plant started,
contributing to increase the reliability, security, stability in operation,
power quality for the regional power system and limit power transmission loss,
increase production and business efficiency in power sector.

Commencement
of 220kV Dak Nong substation
Up to now, CPMB started 10 projects, which
indicates the high efforts by CPMB staff in particular and EVNNPT in general in
order to welcome the power sector traditional day 21st December and response to
“customer gratitude” month – December 2016 by Vietnam Electricity (EVN) and
EVNNPT.
Some
basic information:
1. 220kV Luu Xa substation
- Comtractor: Song Da Installation and Services
Joint Stock Company .
- Total investment cost: VND 269.699 billion.
- Scope of works: (i) New construction of a
220kV substation, of two 220kV-250MVA transformers, with 1 transformer
installed in this period; (ii) Construction of 220kV transmission line section,
of a 0.94km length connecting from 220kV Luu Xa substation to 220kV Thai Nguyen
– Phu Binh transmission line; (iii) Construction of a 220kV transmission line
of 727.8m length for auxiliary power use purpose.
- Location: Duc Thinh commune, Thai Nguyen
city, Thai Nguyen province.
2. The 220kV Nong Cong substation
- Contractor: Vietnam Installation Joint Stock
Corporation .
- Total investment cost: VND 434.694 billion
- Scope of works: (i) New construction of 220kV
substation, of 02 220kV-250MVA transformers, with 1 AT2 transformer installed
in this phase, 1 AT1 transformer to be installed in phase 2; (ii) Construction
of 2 double circuit 220kV transmission line sections to connect from 220kV Nghi
Son – Thanh Hoa transmission line (circuit 2) to substation in this phase, with
a length of 1,353 m and 1,398 m.
- Location: Huu Can village, Te Loi commune, Nong
Cong district, Thanh Hoa province.
3. The 220kV Phong Dien substation
- Contractor: Song Da Installation and Services
Joint Stock Company .
- Total investment cost: VND 205.140 billion.
- Scope of works: (i) New construction of 220kV
substation, semi-outdoor, semi-indoor, of 2 220kV-125MVA transformers, with 1
transformer installed in this phase; (ii) Construction of a double circuit
220kV transmission line section of a 1,346 m length connecting from 220kV Phong
Dien substation to 220kV Dong Ha – Hue transmission line; (iii) Construction of
one circuit 22kV transmission line of a 936 m length for auxiliary power use
purpose.
- Location: Phong Thu commune, Phong Dien
district, Thua Thien-Hue province.
4. Trạm biến áp 220kV Phù Mỹ
- Contractor: Vietnam Power Installation Joint
Stock Corporation
- Total investment cost: VND 241.311 billion.
- Scope of works: (i) New construction of 220kV
substation, of two 220kV-125MVA transformers, with 1 transformer installed in
this phase; (ii) Construction of 220kV distribution system including 8 feeders
and 110kV distribution system including 15 feeders; (iii) Construction of
double circuit 220kV transmission line, with total length of about 1.712 km connecting
to the 220kV Quang Ngai – Quy Nhon transmission line which is under
construction; (iv) Construction of a circuit 22kV transmission line of about 668m
length for auxiliary power use purposes.
- Location: Trung Hoi village, My Trinh
commune, Phu My district, Binh Dinh province.
5. The 220kV Dak Nong substation
- Contractor: Power Installation One-Member
Limited Liability Company 2.
- Total investment cost: VND 364.085 billion.
- Scope of works: (i) New construction of 220kV
substation, of 02 220kV-125MVA transformers; (ii) Construction of a double
circuit 220kV transmission line, of a 1.19 km length, separating 1 circuit from
220kV double circuit transmission line at 500kV Dak Nong substation to 220kV
substation at Aluminum power plant; (iii) Construction of 220kV transmission
line of a 0.45 km length for auxiliary power use purpose.
- Location: Village 12, Nhan Co commune, Dak
R’lấp district, Dak Nong province.