Energizing the 2nd 220kV transformer at 220kV Bao Thang substation

Chủ nhật, 29/7/2018 | 08:25 GMT+7
​At 20h45 on July 26th 2018, at Phu Nhuan commune, Bao Thang district, Lao Cai province, the Northern Power Projects Management Board (NPMB) combined with relevant units have energized the 220/110/22kV-250MVA transformer, completing project “Installing the 2nd 220 kV transformer at 220kV Bao Thang substation”.

M2BT_270718.jpg
​The AT2 220/110/22kV-250MVA Bao Thang transformer. Photo by Ngo Minh Tung.​​

The completion of project will contribute to provide a secure and stable power supply to load centre of Lao Cai province, strengthen the reliability and transmission of the national power transmission grid.

This is under project “Installing the 2nd transformer at 220kV substations of Ha Giang, Tuyen Quang, Bao Thang”.

This is the Level 1, Group B energy project, with total cost of over VND 199.3 billion invested by National Power Transmission Corporation. The project management is done by NPMB on behalf of EVNNPT, project design is done by Power Engineering Consulting Joint Stock Company (PECC1); Van Thach Limited Liabilities Company is responsible for project implementation; Power Transmission Company No. 1 takes over the manavement and operation when the project is completed.

Scope of project: Installing a 3 phase 220/110/22 kV – 250 MVA autotransformer in the 220kV Bao Thang substation, increasing total capacity of substation to 2x250MVA; installing equipment to one 220kV feeder, one 110kV feeder, surge arrester and an outdoor 22kV power transformer for the new installed tranformer./.