Participation in the meeting includes Mr.
Nguyen Dinh Tho - Deputy Director of
CPMB, representatives of implementing unit -
Power Construction Company 2 (PCC2), representatives of monitoring consulting
company and Power Transmission Company No. 3 (PTC3) and some relevant units.

Ground
Breaking ceremony of the 220kV Thap Cham substation (Transformer 2)
The 220kV Thap Cham substation project
(transformer 2) has a total investment cost of VND 74.06 billion, mobilized
from commercial credit and equity of National Power Transmission Corporation
(EVNNPT). The project is invested by
EVNNPT, CPMB is on behalf of EVNNPT to manage the project.
The construction investment of project is to
protect against overload for a 220kV-125MVA transformer at 220kV Thap Cham
substation; ensure a secure operation, increase reliability of power system to
meet power load of Ninh Thuan province; reduce power loss, contributing to
increasing the power production and business efficiency of EVN and EVNNPT.
Scope of project: (i) Installing the 2nd AT2
220kV-125MVA transformer and feeders 220 kV, 110 kV and 22 kV; (ii) Installing 02
feeders 110kV; (iii) Supplementing, completing the measurement, protection
control system and other relevant system .
Location of project: At spare area inside the
existing 220kV Thap Cham substation in Ba THap village, Bac Phong commune, Thuan
Bac district, Ninh Thuan province.
After the ground breaking ceremony, CPMB
focused on instructing, managing, combining with the relevant units to organize
the implementation, with a target of energizing project in December 2017 as
scheduled, ensuring a secure operation, increase the reliability to meet the
power load of Ninh Thuan province./.