Energizing 500kV Ha Tinh substation after overhaul of AT2 transformer

Thứ tư, 16/11/2016 | 17:25 GMT+7
​​Carrying out the 2016 overhaul, from June 24th 2016 to July 21st 2016, Ha Tinh Transmission Division (under Power Transmission Company No. 1- PTC1) combined with Anh Duong – Sai Gon Industrial Technical Limited Liabilities Company overhauled successfully the AT2 - 500​ kV transformer at the 500 kV Ha Tinh substation.

After 27 days of overhauling AT2 - 500 kV transformer, under the serious and strict technical procedures, at 23h00 on July 23rd 2016, at 500kV Ha Tinh substation, Power Transmission Company No. 1 combined with relevant units successfully energized the AT2 - 500 kV tra​​nsformer.

Participation in the project includes Anh Duong - Sai Gon Technical Industrial Limited Liability Company combined with Ha Tinh Power Transmission, Equipment Repair Division, Testing Division. Besides, the project is provided with regular guide and instruction by Board of Directors and various Divisions of PTC1.

DaituAT2500HTinh_250716_1.JPG
Overhauling the AT2 transformer at 500 kV Ha Tinh substation

The overhaul of AT2 transformer at 500 kV Ha Tinh substation help to settle shortcomings occurred to AT2 transformer such as high concentration of gas in oil in Phase B, Phase A, oil leakage in Phase C. Besides, the overhaul helped to find out 1 point where power discharge occurs in Phase B…

The successful energization of AT2 transformer of 500 kV Ha Tinh substation after overhaul has contributed to increasing the reliability in operation and secure power supply to the North Central provinces in general and Ha Tinh province in particular. A secure operation of 500 kV Ha Tinh substation was ensured, this is a very important substation in the national power transmission system and is a premise for PTC1 to settle the other 500kV transformers which have shortcomings and failures in PTC1./.