Energizing the 500 kV - 128 MVAr shunt reactor at 500kV Vung Ang substation

Thứ năm, 17/5/2018 | 09:10 GMT+7
​At 21h20, on 13th May 2018, at the 500kV Vung Ang substation, Power Transmission Company No. 3 (PTC3) coordinated with the relevant units to energize and put into operation the 500 kV - 128 MVAr KH591 shunt reactor.

KH591VA_160518_1.JPG
The 500 kV - 128 MVAr reactor at 500 kV Vung Ang substation

This is one of 6 shunt reactors in project “Equiping shunt reactors in the 500kV transmission grid” invested by National Power Transmission Corporation (EVNNPT) with a scale of six 500 kV - 128 MVAr reactors and related equipment connecting to the 500 kV bus bar system at six 500 kV substations: Cau Bong, Song May, Di Linh, Dak Nong, Pleiku 2 and Vung Ang.

After successful energizing, the KH591 shunt reactor of 500 kV Vung Ang substation has brought into full play the efficiency of project, the busbar voltage at 500 kV Vung Ang substation always remains stable in the operating voltage range.

The project efficiency will increase flexibility in voltage adjustment of power system in general and the 500 kV grid in particular; enhancing the ability in a safe, stable and reliable operation, contributing to reducing losses on power transmission grid; increasing transmission capacity on the 500 kV transmission line sections and ensuring quality of power for the country's economic and social development.

The success energization of project has contributed to the emulation to achievement of celebrating the 128th birthday of President Ho Chi Minh and the 10th anniversary of the establishment of National Power Transmission Corporation (1/7/2008 - 1/7/2018) in PTC3.

Before this event, on 22nd March 2018, 25th April 2018 and 27th April 2018, the 500kV- 128 MVAr shunt reactors were energized in the 500kV substations of Di Linh, Pleiku 2 and Dak Nong by PTC3./.