Energizing the 2nd 220kV-250MVA transformer at Bac Ninh 3 220 kV substation
Thứ ba, 16/1/2018 | 09:40 GMT+7
At 04h40, on January 12th 2018, at
Cho town, Yen Phong district, Bac Ninh province, the Northern Power Projects
Management Board (NPMB) combined with the relevant units to energize the 2nd 220/110/22kV-250MVA
transformer (AT2) at Bac Ninh 220 kV substation, completing the project
"Installation of 2nd 220kV transformer at Bac Ninh 3 220kV
substation".

The AT2 220kV-250MVA transformer before energization
The energized 2nd 220kV-250MVA AT2
transformer at Bac Ninh 3 220 kV substation will contribute to ensure a secure
and stable power supply to the loads of Bac Ninh city, especially Yen Phong
industrial zone and Sam Sung electronic consortium, contributing to pushing up
the socio-economic development of the area.
This is the energy project of Level
1, Group C, with a total cost of over VND 72 billion invested by the National
Power Transmission Corporation (EVNNPT);
NPMB was on behalf of EVNNPT to
coordinate the management of project; Power Engineering Consultation Company 2
(PECC 2) was responsibile for project design; Song Da Joint Stock Installation
and Services Company was responsible for implementation; Power Transmission
Company 1 (PTC1) takes over the operation of project.
Scope of project: a new
installation of a 220/110/22 kV AT2 transformer of a 250 MVA capacity (to
increase the total capacity of Bac Ninh 3 220kV substation to 2x250 MVA); installation
of a 220 kV feeder, a 110 kV feeder, devices to the 22kV side of the newly
installed transformer./.