Energizing and putting into operation of the 500kV Lai Chau substation and branch

Thứ ba, 3/4/2018 | 14:25 GMT+7
​At 23h12, on April 1st 2018, at the 500kV Lai Chai substation, the Central Power Projects Management Board (CPMB) in combination with the relevant units organize energizing and putting into operation the 500kV Lai Chau substation and branch.

​​500LC_020418_1.jpg
The AT2 500/220/35kV-450MVA tranform​er at the 500 kV Lai Chau substation

The energizing and putting into operation the 500kV Lai Chau substation and branch will evacuate capacity of the hydropower plants in Lai Chau and Son La provinces into the national power system; strengthen the power system connection of Lai Chau province with the national power system; reduce the general loss of the system, strengthen the reliability, stability and security of the entire power system.

The project has a total cost of VND 777 billion invested by the National Power Transmission Corporation (EVNNPT); CPMB is on behalf of EVNNPT to manage the project; Power Engineering Consultation Company 4 (PECC4) is responsible for project design; Electricity Testing and Research Centre (ETRC) is responsible for  testing and calibrating; Power Construction Company No. 4 (PCC4) is responsible for project implementation; Joint Ventrure EVN International and Power Engineering Consultation Company No 1 (PECC1) take the responsibility of monitoring and consultation; Power Transmission Company No. 1 (PTC1) takes over the management and operation after project completed.

Scope of project: (i) New construction of a out-door 500kV Lai Chau substation, with 02 500/220/35kV-450MVA transformers and other 02 220/110/22kV-250MVA transformers. In the first phase, installing one 500/220/35kV-450MVA and one 220/110/22kV-250MVA transformer, 02 feeders at 500kV, 02 feeders at 220 kV, 06 feeders at 110 kV, the overall feeder at 500 kV, 220 kV, 110 kV and 22 kV, the coupler circuit breakers, transfered circuit breakers at 220 kV, 110 kV and spare space for installing feeders in future; (ii) Constructing a double circuit 500kV transmission line section, of a length of 1,547 m connecting from the 500 kV Lai Chau substation to the 500 kV Son La – Lai Chau transmission line.

The project location is at Nam Hang commune, Nam Nhun district, Lai Chau province./.​