Second circuit of
the 220kV Di Linh – Bao Loc transmission line
This is the I
class energy project of group B with a total investment cost of over VND 168
billion, invested by the National Power Transmission Corporation (EVNNPT). PTC3 is on behalf of EVNNPT to manage
and operate the project. The Power Engineering Consulting Joint Stock Company 3
is responsible for project design. Vietnam
Joint Stock Power Construction Corporation (VNECO) is responsible for project
implementation. Power Transmission Company No.3. Lam Dong power transmission
Branch (belong to PTC3) is responsible for implementation supervision, taking
over, management and operation after the completion of the project.
Scale of the
project: (i) To build 01 new second circuit of the 220kV Di Linh - Bao Loc transmission lines with a total length of
34.4km, including 92 electric tower, passing through 3 districts and cities: Di
Linh, Bao Lam and Bao Loc city; (ii) To build new 01 of 220kV outgoing feeder at
500kV Di Linh substation (initial point) and 01 of 220kV outgoing feeder at 220kV Bao
Loc substation (final point).
The
energizing and putting into operation of the second circuit of the 220kV Di
Linh – Bao Loc transmission line will contribute to the transmission power
capacity from Da Nhim hydro power plant, Dai Ninh, Dong Nai 2 to the national
power system will improve reliability, stable and safe power supplying for
districts and cities in the region; It also reduces the overload for the
existing single circuit 220kV Di Linh - Bao Loc transmission line. It will form
the linkage of 220kV power system between the central and southern regions to
the period after 2025.