Energizing and commissioning the 220kV Ben Tre – Mo Cay transmission line project

Thứ ba, 23/6/2015 | 00:00 GMT+7
​​At 12h40, on June 11th 2015, at the 220kV Ben Tre substation, Southern Power Projects Management Board (SPMB) combined with consulting, construction, management companies organized energizing and commissioning the 220kV Ben Be – Mo Cay transmission line project and 2 feeders at the 220kV Ben Tre substation. The project has been completed 2 months ahead schedules. This project has been registered by SPMB as a typical one to be honour of EVNNPT’s session II Party Congress, term 2015-2020.
DZ 220kV Ben Tre - Mo Cay_11-6-2015_1.jpg 
The 220kV Ben Tre – Mo Cay transmission line: Conductor stringing is under implementation

The scope of project is to build a new double-circuit 220kV transmission line, of a length of 2x19.7km (from the 220kV Ben Tre substation to 220kV Mo Cay substation) and expand 2 feeders at 220kV Ben Tre substation. The project runs through area of Ben Tre city and districts of Mo Cay Nam, Mo cay Bac of Ben Tre province.

The project has a total cost of over VND 482 billion, invested by EVNNPT; SPMB is on behalf of EVNNPT to manage the project; Project design  is done by Power Engineering Consultation Company No. 3 (PECC3), Project implementation is done by Power Consulting Company No. 1 (PCC1). After the project is completed, management and operation of project will be done by Power Transmission Company No. 4 (PTC4) .

The project construction is to provide a stable power supply to the national defense, socio-economic development of Ben Tre province and surrounding areas. The 220kV Ben Tre – Mo Cay, together with 500kV Duyen Hai substation, 500kV Duyen Hai - My Tho transmission line, 220kV Duyen Hai - Mo Cay transmission line (expected to be completed in 2015) will evacuate entire capacity of Duyen Hai Power Centre into the national power system, creating a stable linkage between Duyen Hai Power Centre and the 500kV/220kV transmission lines, which ensures a stable power supply to the South-Western area.

The efforts made by SPMB staff who spent weekends to settle the difficulties, outstanding in compensation, site clearance for 687 affected households, as  well as the fact that project completed 2 months before schedule have shown high efforts, determination by entire SPMB staff in emulation movement to complete project to be honour of EVNNPT’s session 2 Party Congress, term 2015 – 2020./.