The 500kV Vung Ang – Ha Tinh, Da Nang transmission line (branch 1) was energized and put into operation

Thứ năm, 11/6/2015 | 00:00 GMT+7
​At 06h56 on April 28th 2015, the 500kV Vung Ang – Ha Tinh, Da Nang  transmission line (branch 1) was energized and put into operation by the National Power Transmission Corporation (EVNNPT).
DZ 500kV Vung Ang - re Ha Tinh, Da Nang_28-4-2015.jpg
The 500kV Vung Ang, Ha Tinh, Da Nang transmission line (branch 1) was under installation

Putting the 500kV Vung Ang – Ha Tinh, Da Nang transmission line (branch 1) into operation will bring into full play capacity of the 2000A series capacitors in the 500kV North – South transmission line, upgrading the loading capacity of the 500kV North-South transmission line from 1000A to 2000A, evacuating power capacity from the North to Central area and from Central area to the South, which ensures a stable power supply to Ho Chi Minh city and Southern provinces in 2015 dry season and subsequent years; reduces the power system losses; increases reliability, stability and security in operation of the National power system, evacuates capacity of Vung Ang 1 Thermal Power Plant.

The 500kV Vung Ang- Ha Tinh, Da Nang transmission line (branch 1) is a double-circuit one, from switching yard of 500kV Vung Ang Power Centre to the existing 500kV Da Nang- Ha Tinh transmission line (circuit 1). It has a length of 17.02km, including 42 tower locations, running through communes of Ky Loi, Ky Trinh, Ky Hung and Ky Hoa of Ky Anh district, Ha Tinh province.

The project is invested by EVNNPT. CPMB (Central Power Projects Management Board) is assigned by EVNNPT to manage the project. Power Engineering Consultation Company 2 (PECC2) is designer. Contractors participated in project implementation include Joint Venture of Power Construction and Installation Stock Company and Thang Long Industrial Machinery Installation and Trade Stock Company; Joint Venture of Machinery Installation Stock Company and Local Power Limited Company. Power Transmission Company No. 1 is responsible for the operation management.

The 500kV Vung Ang – Ha Tinh, Da Nang transmission line (branch 1) project has a total investment cost of VND 493.130 billion, using a credit of VND 394.5 billion from Sai Gon- Hanoi Trade Joint Stock Company (SHB), West Hanoi branch and EVNNPT’s equity./.