Implementing the projects “2nd circuit of 220kV Dong Hoi – Dong Ha transmission line” and “2nd circuit of 220kV Dong Ha – Hue transmission line”

Thứ hai, 5/12/2016 | 16:45 GMT+7
​On November 5th 2016, the Central Power Projects Management Board (CPMB) organized ground breaking for 2 projects: (i) “2nd circuit of 220kV Dong Hoi – Dong Ha transmission line” at location 69 (Rao Da village, Truong Xuan commune, Quang Ninh district, Quang Binh province) and (ii) “2nd circuit of 220kV Dong Ha – Hue transmission line” at location 204 (Kim Son village, Thuy Bang commune, Huong Thuy town, Thua Thien Hua province).

Participation in the ground breaking ceremony of project “2nd circuit of 220kV Dong Hoi – Dong Ha transmission line” includes Mr. Le Thanh Dinh – CPMB’s Vice Director and representatives of project implementing unit (Power Construction Company No. 4), project monitoring unit (Power Transmission Company No. 2), leaders of Quang Ninh District People’s Committee, Land Fund Development Centre of Quang Ninh district, Truong Xuan Commune People’s Committee. ​

KCDHDH_051116_1.jpg
Ground breaking in 2nd circuit 220kV Dong Hoi – Dong Ha transmission line project

Participation in ground breaking ceremony includes Mr. Le Dinh Quang – CPMB’s Vice Director and representatives of contractors: Power Construction Company No. 4 (PCC4), Power Engineering Consultation Company No. 3 (PECC3), leaders of People’s Committee of Huong Thuy commune, leaders of Land Fund Development Centre of Huogn Thuy commune, People Committee of Thuy Bang commune.

KCDHH_051116_2.jpg
Ground breaking in 2nd circuit 220kV Dong Ha – Hue transmission line project

The 2nd circuit 220kV Dong Hoi – Dong Ha transmission line project has a total investment cost of VND 450.957 billion, while the 2nd circuit 220kV Dong Ha – Hue transmission line project has a total cost of VND 598.460 billion, mobilized from domestic commercial banks and EVNNPT’s equity. The two projects are invested by EVNNPT, CPMB is on behalf of EVNNPT to manage the projects.

After the ground breaking ceremony, CPMB focused on guiding, managing, coordinating closely with relevant units to organize implementation in order to complete and energize projects as scheduled, meeting timely the load development demands, strengthening the on-site power supply to Hue, Quang Tri and surrounding areas, increasing mobilization of power supply to the South to the year 2020 and completing 220kV grid connection in the area, ensuring a secure, uninterrupt power supply in power system.

Basic information on projects:

2nd circuit 220kV Dong Hoi – Dong Ha transmission line project is constructed to contribute to evacuate capacity of Vung Ang 1 Hydropower Plant when 500kV power grid failures occur connecting to the 500/220kV Vung Ang substation, strengthening power transmission of 220kV transmission network, increasing capacity mobilized for the South to year 2020, increasing reliability in power supply and avoiding overload in regional power grid, which is in accordance with the National Power Development Plan in 2011-2020 period, with consideration to year 2030 approved by the Government at Decision No. 1208/QĐ-TTg dated July 21st 2011.

-  The project has a total investment cost of VND 450.957 billion, with a scope: (i) New construction of 2nd circuit 220kV Dong Hoi – Dong Ha transmission line, with a total length of 107.98 km; (ii) New construction of 1 220kV feeder at 220kV Dong Hoi substation.

- Construction location: The 2nd circuit 220kV Dong Hoi – Dong Ha transmission line route located in Dong Hoi city, Quang Ninh, Le Thuy districts of Quang Binh province; Vinh Linh, Gio Linh, Cam Lo district, Dong Ha city, Trieu Phong of Quang Tri province.

2nd circuit 220kV Dong Ha – Hue transmission line is constructed to strengthen the on-site power supply to Hue, Quang Tri and surrounding areas, creating a 220kV double circuit axis along Central coastal areas linking all Central provinces from Vung Ang thermal power centre of Ha Tinh province to Central South area (Thap Cham – Ninh Thuan) to increase the North-Central transmission capacity, completing the regional 220kV grid connection, strengthening the linkage, supporting capacity among regions, reducing power loss in system, protecting overload for the existing 220kV Dong Hoi – Dong Ha – Hue transmission line when it is in normal operation, especially when failures occur, ensuring a secure, uninterrupted power supply to the regional loads in all situations, including failures occur, which need to mobilize high transmission capacity between the North Central area and South Central area.

The project has a total investment cost of VND 598.460 billion, with a scope: (i) New construction of a 220kV double circuit transmission line, of a total length of 78.2 km from existing 220kV Dong Ha substation to existing 220kV Hue substation; (ii) Improving the connection diagram in existing 220kV side at 220kV Dong Ha substation, equipping 2 transmission line feeders (1 for Hue and 1 for Dong Hoi), 01 communication feeder and loop circuit breaker; (iii) Expanding land area and 220kV bus bars at 220kV Hue substation, installing 1 transmission line feeder for Dong Ha and 2 spare feeders.

Location: the 2nd circuit 220kV Dong Ha – Hue transmission line route is constructed in districts of Trieu Phong, Hai Lang and Quang Tri town of Quang Tri province; Phong Dien district, Huong Tra town, , Huong Thuy town and Hue city of Thua Thien Hue province.​