The project has a total investment cost of VND 162.72 billion, taken
from World Bank (WB) loan and equity of National Power Transmission Corporation
(EVNNPT). The project is invested by EVNNPT, CPMB is on behalf of EVNNPT to manage the project.
The project is constructed to connecting the 220kV transmission lines
in Binh Dinh province in order to create a linkage of power transmission grid
in the area. In future, it will be updated to a substation to meet the load
growth demands and socio-economic development in Binh Dinh province.
The scope of project: To construct a 220kV switching substation, with a
land spared for upgrading to a 220/110/22kV substation of 2x250MVA capacity. In
this phase, a 220kV switching substation is constructed, with a 220kV
distribution system of 4 feeders, 11 spare feeders; construction of 2 sections
of 220kV transmission line of about 830m (475m and 355m) connecting to the
220kV An Khe-Quy Nhon transmission line (circuit 2); construction of 22kV
transmission line 1 circuit of a 4,163 m length to supply power for its
auxiliary purpose.
After the breaking celebration, CPMB focused on guiding, managing and
cooperating with relevant units to organize the project implementation, aiming
at commissioning and energizing project as scheduled, ensuring the requirement
on connecting the 220kV transmission lines in Binh Dinh province in order to
strengthen the regional linkage./.