Energizing and putting into operation the 220kV transformer at 500kV Ha Tinh substation

Thứ ba, 2/8/2016 | 00:00 GMT+7
​​At 15h00 on July 9th 2016, at the 500kV Ha Tinh substation, National Power Transmission Corporation (EVNNPT) energized and put into operation the 2nd 220 kV transformer of 125 MVA, at 220/110/11kV of AT3 substation, completing project “Installing the 2nd 220kV-125MVA transformer at 500 kV Ha Tinh substation".
MBAAT3_500HT_170716.jpg
The AT3 220kV-125MVA transformer

The 2nd 220kV transformer of 500 kV Ha Tinh substation put into operation in parallel with AT4 transformer which energized in 2002 and the improvement of 110kV feeder outline will ensure the load demand, increase the stability, flexibility and reliability on power supply to Ha Tinh province and surrounding areas.

The project has a total cost of nearly VND 68 billion invested by EVNNPT; Northern Power Projects Management Board (NPMB) on behalf of EVNNPT manages the project; Power Engineering Consultant Company No. 1 (PECC1) is responsible for project design; Ha Tinh Power Transmission (under Power Transmission Company No. 1) is responsible for supervision consultation and takes over the project management and operation; Song Da 11 – Thang Long one-member limited liability company is in charge of project construction.

The project is implemented at the hottest time of summer, the temperature at site was often over 40oC. However, with the close instruction by leaders of EVNNPT, PTC1, Ha Tinh Power Transmission as well as efforts by all staffs, the implementing units have overcome difficulties to complete the project ahead scheduled./.

Operations

Operations

Investment

Investment

International relations

International relations

Event Calendar

Event Calendar